CVS Building tenants should be advised of the following:

  1. Soft select demo in select areas of the second floor of Rosemary has started.
  2. Town demo permits have been received. The third floor demo will commence shortly and more details will be provided. This work will still not include asbestos abatement, just walls/etc. The baseline schedule is:
    1. Third floor Rosemary
    2. Third floor Franklin
    3. Fourth floor Rosemary
    4. Second floor Rosemary
  3. Once demo is complete, containment will commence for the abatement. Once the containment is compete, a schedule for abatement will be posted. At this point, all documents will be provided regarding the abatement procedure.