CVS Building tenants should be advised of the following schedule of construction work:

Current Activities

  • 3rd Floor Franklin Demo
  • 3rd Floor Franklin Containment and barricades
  • 3rd Floor Franklin Penetrations infilled with concrete
  • 3rd Floor Franklin Negative air and filtration
  • 3rd Floor Franklin Containment Inspection
  • 3rd Floor Rosemary Demo
  • 3rd Floor Rosemary Plumbing isolation
  • 3rd Floor Rosemary Containment and barricades
  • 3rd Floor Rosemary Penetrations infilled with concrete
  • 3rd Floor Rosemary Negative air and filtration

Upcoming Activities

3rd Floor Franklin and Rosemary Containment Inspection
8/12
Associated Air monitoring
8/12
3rd Floor Franklin and Rosemary abatement
8/12 for Franklin only. Rosemary no earlier than 8/19
Close Rosemary sidewalk for scaffold and trash chute
8/15
3rd Floor Franklin and Rosemary plumbing and electrical rough-ins
TBD
3rd Floor Franklin and Rosemary Bathroom demo
TBD
HVAC work on the 6th floor (non-leased) side
TBD